Souder 138 kV ExtensionTransmission Line Project


AEP Ohio representatives plan power grid upgrades in New Albany in Franklin County.

  • Building Souder Substation off Souder Road in New Albany.
  • Building just over a mile of 138-kilovolt (kV) transmission line*

Company representatives plan to build the transmission line in an approximate 100-foot right-of-way corridor and acquire new easements to ensure the safe construction, operation and maintenance of the line.

The existing electrical network in this area has reached its capacity. The new power line and substation provide an additional power source to ensure reliable electric service for residential and commercial customers and support economic development in the area.

Crews expect to begin construction in fall 2025 and conclude in summer 2026.

*Requires Ohio Power Siting Board (OPSB) approval

Project Updates

August 2025: AEP Ohio representatives announce the Souder 138 kV Extension Transmission Line Project. AEP Ohio officials have filed the new transmission line with the Ohio Power Siting Board (OPSB) as the Souder 138 kV Extenstion Transmission Line Project, Public Utilities Commission of Ohio Case No. 25-0704-EL-BLN.

Property owners along the power line route will be contacted by O.R. Colan (ORC), the right-of-way vendor representing AEP Ohio for this project. If you want to reach out to a right-of-way agent with immediate questions, please contact Joe Greene with OR Colan at 614-340-8233 or Jgreene@orcolan.com.

Project Releases

Timeline

 
Project Timeline
 

Structures

Structure

The project involves the use of steel single-pole structures.

Typical Pole Height: Approximately 120 - 165 feet*
Typical Right-of-Way Width: Approximately 100 feet*

*Exact structure types, height and right-of-way may vary

Resources

Property Easements Project Fact Sheet Project Map Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

Stephanie Eisenberg

WSP representing AEP Ohio
614-259-8201
Outreach@AEPOhioTransmission.com

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.